                 Actions intend to improve access to local building materials
• Kumba-Mamfe road (150.5 km), consisting of several lots: Lot 1: Kumba-Nfaitock: Section 1, executed at 45% and Section 2 at 80%; Lot 2: Nfaitock-Mamfe: Section 3, executed at 60 %.
• Second access road to Bamenda (20 km), exe- cuted at 24%;
• Mengong-Sangmélima road (74 km), executed at 33.9%;
• West agricultural basin service road, 217 km: Lot 1: Baleveng-Galim, 28% completed; Lot 2: Galim-Bamendjing-Foumbot-Banguage: 35%. execution rate;
• Manki-Mapé Bridge road, 21.1 km: 35% pro- gress rate;
• Sangmélima-Ouesso road: Lot 1: Sangmélima- Bikoula (65 km), run at 35%;
• Obala-Batchenga-Bouam road: Lot 1: Nkolessong-Nding, executed at 51.9%, lot 2: Nding-Mbagba, executed at 30%;
• Second bridge over the Wouri: Completion of construction and equipping of the railway via- duct and, completion at 95% of the road viaduct construction work.
Besides, the comfort maintenance covers the Yaoundé-Douala section: Lot 1: Yaoundé- Ndoupé (106 km) executed at 78% and lot 2: Ndoupé-Douala (109 km) executed at 10%. The rehabilitation works of the Dja loop (65 km) on phase 2, for Ngolbang-Zoétélé and Sangmélima-Mezesse-Meyomessala routes are 62% completed.
As regards the PLANUT, the routes to be asphal- ted are decided within the framework of a defi- nite section and cover 10 sections, that is one per region, for an overall length of 677 km. Work is under development on five sections divi- ded into seven lots: Maroua-Bogo (39 km), Douala-Bonépoupa (45 km), Bonépoupa- Yabassi (50 km), Ekondo Titi-Kumba (60 km), Mandjou-Ekokam ( 45 km), Ekokan-Batouri (45 km), Soa-Esse-Awae (72 km).
A number of road development projects are currently in progress